18. M and N complete a piece of work in 15 days and 10 days, respectively. they both together start doing the work but after 2 days N takes leave and M does the rest piece of work alone. The total number of days to complete the work is 19/05/2023 Puspa Kakati 12 days Language: English Post Views: 16